Connection of a service line D 160 SDR 17 PEHD to a main line D 315 SDR 17 PEHD Pipe for new inside hydrants line
Connection of a service line D 160 SDR 17 PEHD to a main line D 315 SDR 17 PEHD Pipe for new inside hydrants line.
Beneficiary: Municipal Police Department from Timisoara
Contractor: Best Instal Srl Timisoara
Solution chosen: SA UNI D 315-400 with outlet D 160 and hot tapping thru a gate valve.
The contractor chose Aliaxis because of the quality experience they had with Aliaxis on site with technical support and quality of the products.
Benefits for the contractor:
- less space required compared with regular connection with reduced spigot tee
- less work and lower cost on digging
- less labour on connection compared with regular service connection
- welding and connection finished in 3.5 hours
- uninterrupted service